Construction Progress
We are excited to keep you informed about the ongoing progress of
The Eyes of Zanzibar, our premier luxury development on this stunning island.
As we move forward with this extraordinary project,
we are committed to providing you with regular and detailed updates to keep you connected to every stage of its evolution.
November 2024
Exciting updates from our construction site! On Block A, we’re making steady progress with the floors rising higher. Meanwhile, on Block B, we’ve moved beyond the initial stages and are making strong advancements in the foundation. Stay tuned for more updates as we continue to build these spaces with dedication and precision!
October 2024
Exciting news! The foundation work for Block Bis now in full swing, marking a major milestone in our construction process. Our team is fully focused on ensuring that the foundation is built to the highest standards, setting the stage for a strong and secure structure. Meanwhile, Block A continues to rise swiftly, with significant progress being made on the upper floors.
Stay tuned for more updates as we continue to develop this exceptional residential complex, offering breathtaking ocean views and first-class amenities!
September 2024
In September 2024, the Zanzibar 5-star residence project at The Eyes of Zanzibar continues its rapid progress, with key structural elements taking shape and excitement building for its completion.
August 2024
In August 2024, the construction of Zanzibar's inaugural 5-star residence at The Eyes of Zanzibar moves into full swing, ushering in a thrilling new phase for the development.
July 2024
In July 2024, the construction of Zanzibar's first 5-star residence at The Eyes of Zanzibar is officially underway, marking an exciting new chapter in the project.
June 2024
In June 2024, the construction of the basement floor at The Eyes of Zanzibar is nearing completion, bringing the project closer to its next major phase.
May 2024
In May 2024, foundation construction at The Eyes of Zanzibar reached a crucial phase.
The reinforcement of Block A's foundation was completed, using approximately 80 tonnes of iron. Shortly after, 300 cubic meters of concrete from "ORKUN" were delivered and poured for Section 3 of Block A, marking a significant milestone that keeps the project on track with its timeline.
April 2024
In April 2024, construction at The Eyes of Zanzibar continued to advance rapidly. The reinforced frame reached 90% completion, solidifying the structure's foundation and setting the stage for the next phases of development. This milestone reflects the steady and focused efforts of the team as the project moves closer to its vision.
March 2024
February 2024 marked key progress at The Eyes of Zanzibar. The team received crucial materials, drilled a well,
and completed thorough geological and magnetic surveys.
The focus was on reinforcing the foundation, with multiple inspections ensuring strength and stability.
A major milestone was achieved with the successful pouring of concrete for the foundation slab,
and the vertical elements of the basement began to take shape, laying the groundwork for future development.
February 2024
The February 2024 construction marks the official start of The Eyes of Zanzibar. The team has been hard at work, ensuring precision in the foundation stages. This month, we've successfully controlled the height position of the foundation pit, meticulously checked dimensions, and outlined the contour for Block A. Despite the challenges of the tough terrain, significant progress has been made, laying a solid foundation for what’s to come.